How a House Is Built in Hyderabad: From Excavation to Handover

If you are building your first house, it helps to know what happens on site and in what order. Here is how an independent house is built, from marking the plot to the finishing work, and why the order matters.

Before the work starts

Good construction starts on paper. Before anyone digs, you should have architectural and structural drawings, a soil report and a site survey. The soil report tells the structural engineer how deep and how wide the foundation needs to be. The municipal permission is applied for by you as the owner, and we guide you through it.

At Hasini Projects, the drawings, soil report, geotechnical report and site survey are listed in every package.

Below ground: the foundation

The foundation carries the weight of the whole house, so this is the stage where care counts most.

Excavation

The layout is marked on your plot, then the ground is dug to the depth set in the structural drawings.

PCC: the base layer

PCC stands for plain cement concrete. A thin, level layer is laid at the bottom of the excavation. It gives a clean, flat surface to work on and keeps the steel away from the soil.

Footings and columns

Steel bars are tied into cages, concrete is poured, and the footings and the columns that rise from them are formed. They carry the load of the building down to the soil.

Underground sump

If your house has an underground water tank, it is built along with the foundation. Building it at this stage makes it strong and properly sealed.

Plinth beam

The plinth beam ties all the columns together at ground level. It spreads the load and keeps the structure from moving unevenly.

Above ground: the structure

Columns and slab

The columns rise one floor at a time, and the slab is cast to form the roof of each floor. This is the stage when the house starts to look like a house.

Brick work

The walls are marked inside and outside, then built to your drawings. Check door and window openings against the plan before the walls go up.

Walls, wiring and plumbing

Electrical and plumbing

Pipes and electrical conduits are fixed into the walls before plastering. That way the walls stay clean and finished afterwards, with no cutting open. Decide switch and socket positions at this point, not later.

Plastering

The walls are plastered smooth inside and out, ready for painting.

Waterproofing

Surfaces that meet water, such as bathrooms, the roof and the sump, are treated so water cannot get through.

Finishing and fittings

Flooring, doors and windows

Floor tiles are laid, and doors and windows are fitted. In our packages the tile and fitting allowances are upper limits: you can choose your own, and pay only the difference if you go above the allowance.

Bathroom fittings and finishing

Bathroom fittings go in, then painting and the final touches. In our packages, false ceiling and lights are quoted separately.

Before and at handover

Rainwater pit

A recharge pit lets rainwater soak back into the ground instead of running off.

Before you accept the house, walk through it with the plan in your hand. Check that the rooms match the drawing, switch and tap positions are right, the doors and windows open smoothly, the floors are level, and nothing leaks when the taps are run. Note anything you find and ask for it to be corrected before handover.

Questions people ask

Why are electrical and plumbing done before plastering?

The pipes and wiring run inside the walls. If they went in after plastering, the walls would have to be cut open and patched, and that leaves marks.

What is PCC in house construction?

Plain cement concrete. It is a thin layer laid under the footings to give a level base and keep the steel off the soil.

Why is the sump built with the foundation?

An underground tank is below ground level, just like the foundation. Building it at the same time is easier, and it is stronger and sealed properly.

Do I get to choose my own tiles and fittings?

Yes. Each package has an allowance. You can choose any brand at any store, and pay only the difference if your choice costs more than the allowance. See the Packages page for details.

How much will it cost?

See our guide to house construction cost in Hyderabad, or the cost for 150 and 200 sq yard plots.

Get a detailed quote

Tell us your plot size and the number of floors you want, and we will send a detailed quote. Call or WhatsApp +91 72072 27595, or use the contact form.

Stages and scope vary with your plot, plan and package. The final scope and price are confirmed in your detailed quote.